What does Procedure Memorandum 43 allow for communities concerning levees?

  1. Immediate funding for levee repairs

  2. 24 months to gather data for levee accreditation

  3. Automatic accreditation of all existing levees

  4. Exemption from federal flood insurance

The correct answer is: 24 months to gather data for levee accreditation

Procedure Memorandum 43 does not authorize immediate funding for repairs to levees, meaning option A is incorrect. Option C is incorrect because all existing levees are not automatically accredited, as this would not be feasible for many communities. Option D is also incorrect since this memorandum does not mention exemptions from federal flood insurance. Option B, however, is correct as Procedure Memorandum 43 does give communities a grace period of 24 months to gather data for accreditation of their levees.